The major purpose of a task link is for rescheduling.
- If we are working on the initial schedule, I don’t suggest to add task link before finalize
- If we are working on rescheduling, if we need to block the link, that means the task link is not useful (or not be created correctly)Also blocking a task will cause the users confused by themselves:
- When moving a task group, if one sub task be blocked, the behavior will confuse the user
- Also similar when change the project start date
- Also this topic is about task linkAn error occurred while saving the comment Jm shared this idea ·
What I’m looking for would be a property of the task start date.
In the existing behavior, if a linked predecessor task is updated to add additional days or the start/end is moved then the subsequent tasks will be automatically moved.
For the behavior I’m suggesting, I want dates that don’t move. Just like you can lock a project, I want a task that is locked and only the items around it can be updated.