Automatic date adjustment on tasks based on predecessor
It nice to visually see the predecessor relationship, but the whole reason for using software (IMHO) is so it can do the work of adjusting dates. I'm surprised this isn't the #1 feature requested.... Or am I missing a setting somewhere....
3
votes
Anonymous
shared this idea
Task link is the existing feature. Pls see more details at http://quickplan.mobilinked.biz/support/help
-
AdminMobilinked (Li, Mobilinked) commented
@Epsen Joranger
Please can you check http://www.quickplan.xyz/documents/quickplan-for-ios/user-manual/project-properties/task-link-behaviour/ ?
-
Espen Joranger commented
Is it corrent that the successors of the task is only adjusted when moving forward and not backwords in time?