Options to disable weekend
Show options to disable weekend before task creation
Hello,
QuickPlan 8.0 is at testing phase, with a new feature to “skip non-working days” when layout task.
http://www.quickplan.xyz/documents/releasenotes/quickplanhd80/
Best regards,
-
Dave commented
In true Gantt project planning the Duration value of an activity is NEVER calculated. It is a static value that is entered by the user. All other values in Gantt chart calculations are a function of activity Durations. The only time a Duration changes is when the user modifies the value based on real world events. (i.e. If a supplier is late on a delivery, If an engineer finishes his/her work ahead of schedule, If the project manager is forced to "crash" the plan to keep the project on schedule, etc...) NonWorkingDays should never change activity Durations.
-
Anonymous commented
I agree. Formatting becomes a challenge once exported. No way to choose the color option and the baby blue isn't professional.
-
Anonymous commented
Yes. Make the task duration stretch based on work and non-working days. Currently, if I move a task with 3 days work and 3 days duration over a week end, the task becomes 1 day work over 3 days duration. It should be 3 days work over 5 days. This will impact the entire planning.
-
Anonymous commented
A major part of a project planer is being able to plan by adding how many working days a given task will take. But when the planner includes weekend and "non work days" in the planning it becomes a problem.
I would consider the option for the app to automatically skip "non work days" to be critical and essential.