Hiding completed tasks (100%)
I'm using QuickPlan Pro for iPad to record changes (ITIL proces). After a changed is delivered and accepted by the customer, I want to hide it from the overview.
Is it possible to add a feature to see all items, see only the open items and see only items by status.
-
AdminMobilinked (Li, Mobilinked) commented
Some users like the way of managing todo tasks to manage schedule, todo and schedule seem similar, but
Project schedule is to guide the team how to do (when start, when finish, who, how much, depends), AND the project schedule should reflect the reality - that means if the tasks are not be completed by schedule, the project should be rescheduled (to make sure the schedule is the reality) - that means if a task scheduled to be completed 100% today, it should be, or it should be rescheduled. There is no more useful if you are using QuickPlan for project schedule, but if you are using it to manage todo task, ...
And logic problem: If a group contain tasks 100% completed and be hidden, so the task group data will be very strange for you to understand
And if you do like the way, just display tasks as list, and sort the % complete column
-
Hans van Benthem commented
I would like to combine it with the predefined list. Would it be an option to make this available by a switch/filter setting on the "% completed" column?