    Ben Fletcher commented  · 

    It seems like activities are scheduled only when creating them initially. During the life of a project, activities will change in duration, start later or earlier than planned, finish later or earlier than planned, additional activities may be required. When any of these things happen the dates for all other successor activities will change. There is currently no option to represent these changes and what the impact is on the duration and dates of the project overall. The option to reschedule is required. This article discusses how this works in other planning tools:

    https://tensix.com/microsoft-project-status-date/

    I am happy to explain further if required.