Does anyone know how i do this.
Example if i have 3 activities with 5 day durations, and they are ~FS relationships.
I change the 2nd (task 2) from 5 days to say 8 days.
This then should move 3rd (task 3) which means the dates will be changed / re-scheduled.
I asked Support but sadly the response was useless - RTF was the reply.
I spent £17 to buy this App in good faith but honestly if i cannot Re-Schedule when I simply change durations, then its only Graphical no Logic Driven Capability.
Maybe i have missed something but honestly Support cannot even help - what hope do we have
Does anyone know how i do this.
Example if i have 3 activities with 5 day durations, and they are ~FS relationships.
I change the 2nd (task 2) from 5 days to say 8 days.
This then should move 3rd (task 3) which means the dates will be changed / re-scheduled.
I asked Support but sadly the response was useless - RTF was the reply.
I spent £17 to buy this App in good faith but honestly if i cannot Re-Schedule when I simply change durations, then its only Graphical no Logic Driven Capability.
Maybe i have missed something but honestly Support cannot even help - what hope do we have