    The major purpose of a task link is for rescheduling.
    - If we are working on the initial schedule, I don’t suggest to add task link before finalize
    - If we are working on rescheduling, if we need to block the link, that means the task link is not useful (or not be created correctly)

    Also blocking a task will cause the users confused by themselves:
    - When moving a task group, if one sub task be blocked, the behavior will confuse the user
    - Also similar when change the project start date
    - Also this topic is about task link

    Andrew Milne supported this idea  · 
    An error occurred while saving the comment
    Andrew Milne commented  · 

    Would it be possible to add a fixed task start date flag which would be auto-set on 100% completion. This flag would have an overriding manual control, so it can be set (or reset manually as required). This would stop completed tasks/milestones and planned tasks/milestones (on a specific date) from moving when moving other linked tasks/milestones. Moving a complete group will not affect fixed tasks/milestones (whether complete or not), only moving unfixed tasks.